A 400/200 volts transformer has pu impedance of 0.05. The HV side voltage required to circulate full load current during short circuit test is
in Electrical Engineering by

1 Answer

0 like 0 dislike

A 400/200 volts transformer has pu impedance of 0.05. The HV side voltage required to circulate full load current during short circuit test is 20 V