In a power generating station the Demand Factor and Load Factor are 0.5 and 0.2, respectively. If the connected load is 400 MW, the average demand is

(A) 40 MW (B) 100 MW (C) 140 MW (D) 280 MW

Buy Product With :- https://amzn.to/2YK7F9b

Your answer

Thanks for your contribution. Feel free to answer this question. Please avoid short answer. Your answer is most welcome. Be genuine.

Upload image or document:

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:
Are you a robot ? (Y = Yes / N = No)
To avoid this verification in future, please log in or register.

1 Answer

0 votes
by

In a power generating station the Demand Factor and Load Factor are 0.5 and 0.2, respectively. If the connected load is 400 MW, the average demand is 40 MW

Buy Product With :- https://amzn.to/2YK7F9b

Welcome to Q&A site for electrical and electronics engineering discussion for diploma, B.E./B.Tech, M.E./M.Tech, & PhD study.
If you have a new question please ask in English.
If you want to help this community answer these questions.

Categories

...