At an industrial sub-station with a 4 MW load, a capacitor of 2 MVAR is installed to maintain the load power factor at 0.97 lagging. If the capacitor goes out of service, the load power factor becomes (A) 0.85 (B) 1.00 (C) 0.80 lag (D) 0.90 lag

1 Answer

0 votes
by

At an industrial sub-station with a 4 MW load, a capacitor of 2 MVAR is installed to maintain the load power factor at 0.97 lagging. If the capacitor goes out of service, the load power factor becomes  0.80 lag

Related questions

1 answer 21 views

A power station supplies the peak load of 60 Mw, 40 MW and 70 MW to three localities. The annual load factor is 0.50 p.u. and the diversity factor of the load at the station is 1.55. The maximum demand on the station and average load respectively will be 

asked Mar 27, 2018 in Power system by Shimroz123
0 answers 44 views

A plant with 10 MW installed capacity produces an annual output of 6 × 6 10 kWh and remains in operation for 2000 hours in a year. The Plant Use Factor is (A) 0.33 % (B) 3.33 % (C) 15 % (D) 30 % 

asked Jun 4, 2018 in Power system by Shimroz123
1 answer 17 views

A generating station has a maximum demand of 50 Mw, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded. The daily energy produced will be

asked Mar 27, 2018 in Power system by Shimroz123
1 answer 14 views

A 3-phase 11 kV generator feeds power to a constant power unity power factor load of 100 MW through a 3-phase transmission line. The line-to line voltage at the terminals of the machine is maintained constant at 11 kV. The per unit positive sequence impedance of the line based on 100 MVA and 11 kV is j0.2. The line to line voltage at the ... load to increase the line-to-line voltage at the load terminals to 11 kV is  (A) 100 MVAR (B) 10.1 MVAR (C) -100 MVAR (D) -10.1 MVAR

asked May 25, 2018 in Power system by Shimroz123
1 answer 23 views

Two synchronous generators operating in parallel supply a common load of 2.5 MW. The frequency-power characteristics have a common slope of 1 MW/Hz and the no-load frequencies of the generators are 51.5 Hz and 51.0 Hz, respectively. Then the system frequency is (A) 50 Hz (B) 51 Hz (C) 51.25 Hz (D) 51.5 Hz

asked Apr 28, 2018 in Electrical Machine by Shimroz123
1 answer 21 views

An 800 kV transmission line has a maximum power transfer capacity of P. If it is operated at 400 kV with the series reactance unchanged, the new maximum power transfer capacity is approximately (A) P (B) 2P (C) P / 2 (D) P / 4

asked May 25, 2018 in Power system by Shimroz123
1 answer 39 views

A generating station has a maximum demand of 500 MW. The annual load factor is 50 percent. The energy generated per annum will be: A) 2.19 x 106 MWhr B) 600 MWhr C) 250 MWhr D) 7.50 x 106 MWhr

asked Jun 17, 2018 in Electric Power Generation by Shimroz123
1 answer 23 views

An industrial consumer hall a daily load pattern of 2000 KW, 0.8 lag for 12 Hra and 1000 kW UPF for 1J Hr. The load factor i= _____. 

asked Mar 27, 2018 in Power system by Shimroz123
1 answer 5 views

List two major equipment at traction sub-station with their functions.

asked Sep 12, 2018 by Shimroz123
0 answers 23 views

A Power system has a total load of 1260 MW at 50 Hz. The load varies 1.5% for every 1% change in frequency. Find the steady state frequency deviation, when a 60 MW load is suddenly dripped if there is no speed control.  (A) 1.667 Hz (B) 50 Hz (C) No change (D) 3.32 Hz 

asked Apr 5, 2018 in Electrical Engineering by Shimroz123
0 answers 20 views

The zero sequence current of a generator for line to ground fault is j 2.4 p.u. The current through the neutral during the fault is (a) j 0.8 p.u (b) j 2.4 p.u. (c) j 0.24 p.u. (d) j 7.2 p.u. 

asked May 25, 2018 in Power system by Shimroz123
0 answers 32 views

In a hydel power station, the number of poles of an alternator is 24. At what rpm the alternator must be driven to produce 50 Hz voltage?

asked Apr 3, 2018 in Lesson 2 Generation, Transmission and Distribution of Electric Power an Overview by Shimroz123
0 answers 19 views

A three phase transmission line delivers a load of 5 MW at 0.8 power factor lagging. Resistance of each conductor is 0.5 ohm / km. Receiving end voltage is 33 kV. If the line loss is not to exceed 10%, determine the length of the line.  (A) 7 km (B) 27.9 km (C) 56.8 km (D) 13.9 km

asked Apr 5, 2018 in Electrical Engineering by Shimroz123
1 answer 20 views

In a power generating station the Demand Factor and Load Factor are 0.5 and 0.2, respectively. If the connected load is 400 MW, the average demand is (A) 40 MW (B) 100 MW (C) 140 MW (D) 280 MW

asked Apr 25, 2018 in Electrical Engineering by Shimroz123
1 answer 33 views

The Lissajous pattern on the screen of a CRO is an ellipse with major axis in quadrant 2 and quadrant 4. Then the phase difference between two signals Can be :  (A) 270° (B) 210° (C) 180° (D) 300°

asked Apr 30, 2018 in Electrical Engineering by Shimroz123
1 answer 25 views

A DC reactor is connected in series with each pole of a converter station in order to: A) prevent commutation failures in the inverter B) supply reactive power to the converter C) improve system stability D) increase the power transfer capability

asked Jun 4, 2018 in Power system by Shimroz123
1 answer 19 views

A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant is   (a) 5 MW (b) 4 MW (c) 6 MW (d) 10 MW 

asked May 13, 2018 in Electrical Engineering by Shimroz123
0 answers 45 views

For a balanced three phase star connected load for which line voltage is 230V and per phase resistance and reactance is 6 Ohm and 8 Ohm respectively. Calculate: 1) phase voltage 2) line current 3) power factor 4) total power absorbed

asked Aug 12, 2018 in Basic electrical and electronics engineering by Quiz
1 answer 42 views

A 50 Hz, 4-pole, 500 MVA, 22 kV turbo-generator is delivering rated megavolt amperes at 0.8 power factor. Suddenly a fault occurs reducing in electric power output by 40%. Neglect losses and assume constant power input to the shaft. The accelerating torque in the generator in MNm at the time of fault will be  (A) 1.528 (B) 1.018 (C) 0.848 (D) 0.509

asked May 25, 2018 in Power system by Shimroz123
1 answer 25 views

A loss less transmission line having Surge Impedance Loading (SIL) of 2280 MW is provided with a uniformly distributed series capacitive compensation of 30%. Then, SIL of the compensated transmission line will be (A) 1835 MW (B) 2280 MW (C) 2725 MW (D) 3257 MW

asked May 25, 2018 in Power system by Shimroz123
0 answers 23 views

The output voltage of a battery drops from 100 V with zero load current to 80 V when load current is 2 A. The internal resistance of the battery is (a) 10 Ω (b) 20 Ω (c) 40 Ω (d) 50 Ω

asked May 25, 2018 in Battery by Shimroz123
1 answer 10 views

For an earth station transmitter, with an antenna output power of 40dBW 10,000W, a back-off loss of 3dB, a total branching and feeder loss of 3dB, a total branching and feeder loss of 3dB and transmit antenna gain of 4dB, the effective isotropic radiated power (EIRP will be  a) 38dBW b) 40 dBW c 36 dBW d) 47 dBW

asked Jun 15, 2018 in Electronics Engineering by Shimroz123
1 answer 28 views

A two -winding single phase transformer has a voltage regulation of 4.5% at full - load and unity power -factor. At full -load and 0.80 lagging power-factor, the voltage regulation will be: (A) 4.5% (B) less than 4.5% (C) more than 4.5% (D) none of the above

asked Apr 11, 2018 in Electrical Engineering by Shimroz123
0 answers 24 views

The sending and receiving end voltages of a three phase transmission line at 100 MW load are equal at 230 KV. The phase line impedance is j14 ohm. Calculate the maximum steady state power that can be transmitted over the line.  (A) 3778.5 MW (B) 2234.56 MW (C) 1784.19 MW (D) 512.37 MW

asked Apr 5, 2018 in Electrical Engineering by Shimroz123
1 answer 12 views

A generating st ation has a maximum, demand of 20 mW, load factor of 60%, a plant capacity factor of 50% and a plant Use factor of 72%. What is the reserve capacity of the plant, if the plant, while running as per schedule, were fully loaded?

asked Mar 27, 2018 in Power system by Shimroz123
1 answer 27 views

Power station having Load factor = 70%, capacity factor = 50%, used factor = 60%, maximum demand = 20MW then annual energy production is  (1) 122.8 GWh (2) 198.55 GWh (3) 128.2 GWh (4) 188.82 GWh

asked Apr 29, 2018 in Power system by Shimroz123
1 answer 31 views

A large AC generator, supplying power to an infinite bus, has a sudden short-circuit occurring at its terminals. Assuming the prime mover input and the voltage behind the transient reactance to remain constant immediately after the fault, acceleration of the generator rotor is

asked Apr 29, 2018 in Power system by Shimroz123
1 answer 20 views

An absolutely integrable signal x(t) is known to have a pole at s = 2. Which one of the following is true ? (A) B, C and D are true (B) x(t) can be left-sided (C) x(t) can be right-sided (D) x(t) can be both-sided

asked May 12, 2018 in Control System by Shimroz123
1 answer 63 views

The inertia constant of a 100 MVA, 11 kV water wheel generator is 4. The energy stored in the rotor at the synchronous speed is: A) 400 Mega Joule B) 400 Kilo Joule C) 25 Mega Joule D) 25 Kilo Joule

asked Jun 4, 2018 in Power system by Shimroz123
1 answer 15 views

A two conductor 1 - pi line operates at 50 Hz.The diameter of each conductor is 4 cm and are spaced 6 m apart. What is the capacitive susceptance to neutral per km?

asked Mar 27, 2018 in Power system by Shimroz123
1 answer 24 views

A single core lead sheathed cable with two dielectrics of permittivity 4 and 3, respectively, are subjected to same maximum stress. If the conductor diameter is 1.5 cm, the outer diameter of the first dielectric is (A) 1.125 cm (B) 1.5 cm (C ) 2 cm (D) 8 cm

asked Apr 28, 2018 in Power system by Shimroz123
1 answer 148 views

A 50 Hz, 4 pole turboalternator rated at 20 MVA. 13.2 KV has an inertia constant H = 4 KW sec/KVA. The K.E. stored in the rotor at synchronous speed is

asked May 3, 2018 in Electric Power Transmission by Shimroz123
1 answer 17 views

A three-phase star -connected load is operating at a power factor angle ϕ  with ϕ being the angle between

asked Apr 25, 2018 in Electrical Engineering by Shimroz123
1 answer 42 views

 An 8-pole alternator runs at 750 rpm and supplies power to a 6-pole induction motor which has a full load slip of 3 percent. The full load speed of the induction motor will be: A) 1000 rpm B) 920 rpm C) 950 rpm D) 970 rpm

asked Jun 4, 2018 in Alternator by Shimroz123
1 answer 16 views

The power delivered to a three-phase load can be measured by the use of 2 wattmeter only when the A. Load is balanced B. 3 -phase load is connected to the source through 3 wires C. Load is unbalanced D. 3 -phase load is connected to the source through 4 wires

asked Apr 12, 2018 in Electrical Engineering by Shimroz123
1 answer 11 views

A two conductor 1 - pi line operates at 50 Hz. The diameter of each conductor is 2 cm and are spaced 3m apart. What is the line to line capacitance ?

asked Mar 27, 2018 in Power system by Shimroz123
0 answers 21 views

A large transformer operating at no load draws an exciting current Io of 5A, when the primary is connected to a 120 V, 60 Hz source. From a wattmeter test, it is known that iron losses are equal to 180 W. Calculate the reactive power absorbed by the core.  (A) 600 var (B) 572 var (C) 180 var (D) 360 var 

asked Apr 5, 2018 in Electrical Engineering by Shimroz123
0 answers 56 views

A power system network with a capacity of 100 MVA has a source impedance of 10% at a point. The fault level at that point is (a) 1500 MVA (b) 1000 MVA (c) 500 MVA (d) 100 MVA

asked May 25, 2018 in Power system by Shimroz123
0 answers 10 views

A bus coupler circuit breaker is utilized in a sub-station for  A) Connecting the transmission line with the bus-bar B) Connecting two power transformers in parallel C) Connecting the bus-bar with ground D) Connecting main and transfer buses in the sub-station

asked Apr 9, 2018 in High voltage engineering by Shimroz123
0 answers 16 views

Output of an op-amp is a square wave of 4 V peak to peak with a rise time of 5 microsecond and fall time of 4 microsecond.Maximum frequency (in kHz)of undistorted sine wave output of 2 V peak to peak is about  A) 100 B) 150 C) 200 D) 250

asked Apr 9, 2018 in Electronics Engineering by Shimroz123
0 answers 23 views

The constant of a given energy meter is 500 revolution/kWh. At the test 4.4 kW full load, meter completes 50 revolutions in 86 seconds. The percentage error of the meter is (a) –4.86% (b) 4.86% (c) 2.0% (d) 3.0%

asked May 26, 2018 in Electrical Measurements and Instrumentation by Shimroz123
1 answer 28 views

 A transformer has maximum efficiency at 3/4 full load. The ratio of its iron losses and full load copper loss is : -  a) 16/9 b) 4 / 3 c) 3/4 d) 9 /16

asked Apr 11, 2018 in Electrical Engineering by Shimroz123
1 answer 249 views

If the reference bus is changed in two load flow runs with same system data and power obtained for reference bus taken as specified P and Q in the latter run, the system losses  A) Will be unchanged but complex bus voltages will change B) Will change but complex bus voltage remain unchanged C) As well as complex bus voltage will changed D) As well as complex bus voltage will be unchanged

asked May 20, 2018 in Power system by Shimroz123
0 answers 21 views

A ramp voltage V(t)=100 V is applied to an RC differentiating circuit with R=5 kΩ and C=4 μF. The maximum output voltage is  (A) 0.2 V (B) 2 V (C) 10 V (D) 50 V

asked Apr 5, 2018 in Electrical Engineering by Shimroz123
1 answer 29 views

If an unsymmetrical line to ground fault occurs at the secondary terminals of a delta/star, ungrounded transformer, then  (A) zero sequence currents are present on both sides of the transformer  (B) zero sequence currents are absent on both sides of the transformer  (C) zero sequence currents are present on the secondary side but not on the primary side  (D) zero sequence currents are present on the primary side but not on the secondary side

asked Apr 29, 2018 in Power system by Shimroz123

Welcome to electronics2electrical.com here you can ask questions related to electrical, electronics, mechanical, telecommunication, instrumentation, computer, mathematics, physics etc.
Be respectful to all the members. Do not copy and paste the answers from other websites which have copyright content. While asking question give full details about it.

Categories

Most popular tags

power motor dc circuit transformer voltage current used system phase resistance factor synchronous load ac energy induction electric generator series frequency between speed capacitor use electrical meter line difference control type mosfet transmission magnetic plant high single instrument bjt unit source advantages function diode and machine winding field define torque parallel amplifier supply shunt thyristor motors electricity arduino maximum time relay armature problem value on transformers types coil diagram state flow ratio material three formula starting direction theorem method emf operating efficiency digital wave microprocessor test instruments inductance loss measure operation connected signal low applications effect single-phase network temperature working constant losses different law wattmeter measuring compare controlled breaker drive device logic rc full switch flux wire resistivity disadvantages free of materials machines angle force converter conductor transistor gain open protection scr core measurement number bridge principle generators reactance circuits negative the friction iron loop short pole battery conservation steam resistors hysteresis computer using analog lines secondary station gate a rectifier inverter linear induced relays nuclear capacitance basic characteristics design direct work rotor electronics ammeter forces diesel damping rlc connection factors capacitors minimum insulation moving regulation running self systems air fault range main stability quality starter igbt eddy alternator ideal rl average 3-phase plants arc thermal error fuzzy biasing dielectric pressure balanced superposition errors copper rotation feedback impedance measured electronic electrons charge inductive transfer explain start off back curve over solar is three-phase tariff locomotive peak bias zener engineering commutator surge conductors rating universal potentiometer density permanent mechanical transducer capacity memory adc excitation two fuse pure harmonics application semiconductor inductor internal pmmc reaction welding resonance traction permeability breakers rms designed electromagnetic si generation brushes switching capacitive shaded rate 1 distribution resistor methods delta star oscillator reluctance simplification algebra 8085 boolean weston dynamometer insulating strength installation definition fuel heating earth units
...