5 views
asked in Electric Power Generation by

A large hydropower station has a head of 324 metre and an average flow of 1370 metre3 / second. The available hydraulic power from this station will be: A) 4.35 MW B) 4.15 MW C) 4.47 MW D) 4.73 MW

Your answer

Thanks for your contribution. Feel free to answer this question. Please avoid short answer. Your answer is most welcome. Be genuine.

Upload image or document:

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.

1 Answer

0 votes
answered by

 A large hydropower station has a head of 324 metre and an average flow of 1370 metre3 / second. The available hydraulic power from this station will be: 4.35 MW