A generating station has a maximum demand of 500 MW. The annual load factor is 50 percent. The energy generated per annum will be: A) 2.19 x 106 MWhr B) 600 MWhr C) 250 MWhr D) 7.50 x 106 MWhr

Please log in or register to answer this question.

1 Answer

0 votes
answered by

A generating station has a maximum demand of 500 MW. The annual load factor is 50 percent. The energy generated per annum will be: 2.19 x 106 MWhr 