A generating st ation has a maximum, demand of 20 mW, load factor of 60%, a plant capacity factor of 50% and a plant Use factor of 72%. What is the reserve capacity of the plant, if the plant, while running as per schedule, were fully loaded?

Your answer

Thanks for your contribution. Feel free to answer this question. Please avoid short answer. Your answer is most welcome. Be genuine.

Upload image or document:

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:
Are you a robot ? (Y = Yes / N = No)
To avoid this verification in future, please log in or register.

1 Answer

0 votes
by

5 MW is the reserve capacity of the plant, if the plant, while running as per schedule, were fully loaded.