A generating st ation has a maximum, demand of 20 mW, load factor of 60%, a plant capacity factor of 50% and a plant Use factor of 72%. What is the reserve capacity of the plant, if the plant, while running as per schedule, were fully loaded?

Please log in or register to answer this question.

1 Answer

0 votes
answered by

5 MW is the reserve capacity of the plant, if the plant, while running as per schedule, were fully loaded.